Complete Streets

Bringing Complete Streets to Swampscott

Complete Streets are streets for everyone, no matter who they are or how they travel—walking, biking, taking transit or driving. Through our Swampscott 2025 : The Master Plan process, the Town of Swampscott identified both the need and public desire to bring Complete Streets principles to the community.

Learn more about Complete Streets and what it means to Swampscott.

Project Schedule

ACTIONTIMINGSTATUS
Swampscott Municipal Employee Training via MassDOT Complete Streets 101February 24, 2016COMPLETE
Letter of Intent to Adopt Complete Streets Policy Submitted to MassDOTAugust 5, 2016COMPLETE
Public Presentation about Complete Streets and Release of Draft PolicySeptember 12, 2016COMPLETE
Complete Streets Policy (Draft) Public Comment PeriodSeptember 12 - October 12, 2016COMPLETE
Board of Selectmen Review of Complete Streets PolicyOctober 19, 2016COMPLETE
Board of Selectmen Vote to Adopt Complete Streets PolicyNovember 2, 2016COMPLETE
Submit Adopted Complete Streets Policy to MassDOT for ApprovalNovember 15, 2016COMPLETE
Selection of Consultant to Develop Prioritization Plan (Howard Stein Hudson)January 2018COMPLETE
Apply for MassDOT Grant for Consultant Services to Develop Prioritization PlanJanuary 2, 2018COMPLETE
MassDOT Approval for Consultant Services Reimbursement FundingFebruary 13, 2018COMPLETE
Start Development of Complete Streets Prioritization PlanMarch 2018COMPLETE
Submit Complete Streets Prioritization Plan to MassDOT for ApprovalSeptember 2018COMPLETE