TIME FOR COMPLETION
SECTION VI:   TIME FOR COMPLETION

For each subdivision or each stage of a staged subdivision, the construction of all ways and the installation of all required municipal services shall be completed within 18 months from the date or receipt of bond or surety by the Board or within two years of the date of approval of the Definitive Plan, whichever is earlier.   Failure to do so shall automatically rescind approval under covenant conditions or rescind approval subject to Section 81-W of the Subdivision Control Laws.